Posted: Monday 29 October, 2007 at 4:44 PM
Nevis Island Administration
    Ground water drilling to commence on Nevis this week
     
     
     
    Drilling equipment for ground water project
    CHARLESTOWN NEVIS (OCTOBER 29, 2007)
    -- Equipment to commence drilling for additional water on Nevis arrived on the island late last week.  Senior scientist to the project, geologist, Dr. Ronald B. Hoag Jr. of Bedrock Exploration and Development Technologies (BEAD) in an interview with the Department of Information on Monday October 29, 2007, said that drilling would commence this week at the first drill site in the Hamilton Estate area which is at a high elevation.
     
    “We received all the equipment which arrived Thursday and was offloaded Friday and Saturday.  We are currently to moving the casings and drill rig up to the first drill site at Hamilton Estate and hope to start drilling in a next day or so. We are going to drill the first well up at Hamilton, that’s an area which needs water, it’s on high elevation and we should be done drilling that location in about 2 weeks,” he said. 
     
    The Geologist explained that much preparatory work had been done ahead of this stage in the water exploration venture.
     
    “We’ve been doing ground water exploration activities which included mapping the island using satellite imagery and underground surveying where we can actually see down in the earth about 400 to 600 meters.  We have done over 15 kilometers of geophysical survey throughout the island we have identified numerous targets that look to be quite favourable,” he said. ~~Adz:Right~~
     
    Dr. Hoag noted that in the next few months, when a number of wells would be operating, his company would run aquifer tests which involved placing a pump in the well and running it for a period of time to observe the reaction of the aquifer.  The results of the tests will be used to ascertain the water quality and whether it would become a sustainable yield.
     
    Under the BEAD contract with the Nevis Island Administration (NIA), the company is expected to develop one million gallons of ground water per day to compliment the current supply now available to the island.
     
    While he addressed the environmental impact and effects on the existing water supply, Dr. Hoag assured that the new wells would be located away from existing wells. He said part of the exploration programme was to identify target areas where non-oriented water could be located and to estimate the amount of ground water recharge in any particular area
     
    This the Geologist explained was to ensure that the wells would not draw more than what goes into the ground so there is no possibility of lowering the water table and having salt water intrusion.
     
    He said the company had already hired a few local persons to assist with the geophysical surveys.  In terms of the project being on schedule, Dr. Hoag said the company had experienced a few setbacks in the geophysical survey.
     
    “In addition the exploration part of the program, the geophysical survey took a lot longer than expected because it is a very difficult island to find large volumes of water so we had to cover a fairly large area…I feel we have some very good targets, we’ll definitely get water.
     
    “I would say probably within two weeks we will know whether the first well is successful.  It should only take less than a week to drill each well, so over the next couple of months we’ll have a very good idea of our success,” he said.
     
    Dr. Hoag assured that the project should be completed or at least, Nevisians would be able to enjoy the first million gallons of water per day by some time in early February 2008.