Javascript Menu by Deluxe-Menu.com

SKNBuzz Radio - Strictly Local Music Toon Center
My Account | Contact Us  

Our Partner For Official online store of the Phoenix Suns Jerseys

 Home  >  Headlines  >  NEWS
Posted: Friday 21 February, 2020 at 11:54 AM

New 400,000 gallon water tank at Hamilton completed, work continues on distribution mains installation

Ongoing trenching work being done on site at the Hamilton Reservoir on February 19, 2020, for the installation of water mains from the new steel gas fused 400,000 gallon water there which will feed Charlestown, Craddock Road and Hamilton Estate
By: NIA, Press Release

    NIA CHARLESTOWN NEVIS (February 20, 2020) -- Work continues apace in the Water Enhancement Project at the Hamilton Reservoir compound, and the installation of distribution mains to and from the newly-constructed steel gas fused 400,000 gallon water tank has commenced.  It will replace the existing fiberglass tank.

     

    During a visit to the work site on February 19, 2020, Mr. Floyd Robinson, Manager of the Water Resource Management Department, spoke to the Department of Information of the status of the project to date.
     
    “Currently we are just now installing the distribution mains to switch over from that old tank that we are going to dismantle after this process is done… We have the distribution mains going towards Craddock Road, and one will be feeding Charlestown proper when the tank is fully commissioned,” he said.
     
    Another component of the project to produce more water for the island included redeveloping the Hamilton well which has been in a state of rest for almost 10 years after it was drilled, due to its high manganese content in the water and could not be used.
     
    The Nevis Water Department conducted tests on the well to ensure that it had retained its ability to provide a robust supply of water.
     
    Mr. Robinson indicated that the tests proved satisfactory.
     
    “We did pump test the well for about a week to make sure that it was still consistent, and we are satisfied that we are going to be able to have sustainable water from that well at about 230 gallons per minute.  That’s equal to over 330 gallons per day.
     
    “So the well test has been completed and we are just waiting for this part of the project to be done [water main installation], and then with the old reservoir being dismantled the filtration system will be installed. The filtration system is going to remove the excess manganese that is currently in the well that we just developed,” he said.
     
    Regarding the installation of the filtration system, Mr. Robinson noted that dismantling of the fiberglass tank is expected to commence during the week of February 24, 2020, once there are no further delays due to the recent out-of-season rains.
     
    “We are looking at dismantling of the tank to start next week. It should take about a week and then shortly after that we will start the construction for the filtration system. The major components of the filtration system are already on island.
     
    “We are awaiting two back wash tanks which are soon to be here but the major components of the system are already on island. It has about five different parts that go together to make the system and…even before everything is here, we can start installing different components. So we are just waiting for the tank to be dismantled and then the filtration system will be erected,” he said.
     
    Construction for the system is expected to take about 30 days once there are no weather delays after which it will be up and running.
     
     
     

    Disclaimer

    This article was posted in its entirety as received by SKNVibes.com. This media house does not correct any spelling or grammatical error within press releases and commentaries. The views expressed therein are not necessarily those of SKNVibes.com, its sponsors or advertisers
     
Copyright © 2024 SKNVibes, Inc. All rights reserved.
Privacy Policy   Terms of Service